New Parkland Hospital
Dallas, Texas
Project Description
Parkland Hospital is one of the busiest public hospitals in the United States, with more than 1 million patient visits each year. But demand for Parkland services continues to grow.
The new 2.5 million-square-foot Parkland campus is located on the north-east corner of Harry Hines Boulevard and Medical District Drive. At nearly twice the size of the current hospital, the new Parkland has been designed to meet the ever-changing needs of Dallas County – one of the largest, fastest-growing regions in the country.
__________________________________________________________________
Our Role
Hatcher Technical worked with post-tensioning hardware supplier VSL, design engineer Datum Engineers, and contractor BARA to perform a constructability review of the nine post-tensioned cast-in-place concrete transfer girders. As part of this review, Jason developed fully integrated 3D CAD models to show all the girder post-tensioning hardware, and integrated reinforcement. With the review complete, Jason worked with the project team, identifying the congestion and areas of concern, and developing appropriate solutions.
Location
Dallas, Texas
Owner
Parkland Health & Hospital System
Contractor
BARA Joint Venture
Balfour Beatty, Austin Commercial, H.J. Russell & Company, and Azteca Enterprises)
Designer
HDR & Corgan Associates (Architect)
Datum Engineers, Gojer & Associates, and AG&E (Structural Engineers)
Post-Tensioning Hardware Supplier
VSL
Total Contract Value
$1.3 Billion
Timeline
2011 - 2015
Construction Method
-
Reinforced concrete structure with post-tensioned beams to support cantilevered section of the building