top of page
PNSY Super Flood Entrance Structure 4 (credit Cianbro) - Banner.jpg

Portsmouth Naval Shipyard (PNSY) Super Flood Entrance Structure

Kittery, Maine

Project Description

 

The super flood entrance structure is a portion of an overall modernization project that aims to create a navigation lock system to reduce tide dependency for submarine movements in and out of the Portsmouth Naval Shipyard’s Dry Dock 1 in Kittery, Maine.

Per the original contract documents, the engineer of record, Stantec, and project owner, the Naval Facilities Engineering Systems Command (NAVFAC), envisioned the structure being cast on land in a dry setting. The completed structure would then be launched and floated into place via waterway and towed behind a barge. The Cianbro team recognized that site conditions presented challenges to constructing the entrance per contract details.

Cianbro’s plan called for casting the structure on a barge at their Ricker’s Wharf facility in Portland, Maine. Due to the project scale, the structure’s sides would hang off the edges of the barge and over the water. The team used almost 2,700 cu yd of self-consolidating concrete—the most Cianbro had ever undertaken on one project. Although massive in scale, the team reduced the weight of the structure’s base by building it with 30 void spaces between an upper and lower slab. As a result, the area from the base of the caisson seat to the top of the structure was a hollow structure with tapered walls.

The strategy enabled the team to successfully transport the entrance on the Fore River and put it in place at the shipyard, where it arrived on June 22, 2021.

 

Once the structure was set in place with strand jacks, the team filled the 5,000 cu yd of void space of the entrance structure—which had an extensive amount of rebar already installed—with marine concrete batched on site. The project completed on time and on budget in May 2022.

Location

Portsmouth Naval Shipyard

Kittery, Maine

Owner

 

United States Navy

Naval Facilities Engineering Command

NAVFAC Mid-Atlantic

Contractor

Cianbro Corp.

Designer

Stantec and Appledore Marine Engineering

Total Contract Value

$158 Million

Timeline

2019 - 2022

Construction Method

110 ft long, 67 ft wide, 60 ft tall precast reinforced concrete engineering structure weighing approximately 5,000 tons.

__________________________________________________________________

 

Our Role

Working with contractor Cianbro, Hatcher Technical started with a thorough constructability analysis of the revised entrance structure. Hatcher Technical then worked directly with NAVFAC, Cianbro, Stantec, and Appledore Marine Engineering to mitigate the constructability issues. This process eased construction in the field, reduced congestion and eliminated redundant reinforcement in some areas.

Hatcher Technical then produced fully integrated 3D models of every separate concrete pour (35 total). From these models, Hatcher Technical developed fully integrated construction shop drawings for each pour. In total, Hatcher Technical detailed nearly 1.2 million lbs of reinforcing steel in 2,650 cubic yards of concrete across 35 separate concrete pours. The reinforcement density was as high as 600 lbs / cubic yard for some sections.

bottom of page